The “Nuovo Scillato” drinking water pipeline is a critical component of Palermo’s water supply system and its eastern coastal region. Constructed in the 1980s, the pipeline was designed to enhance the existing water distribution infrastructure by transporting water from four springs to the Madonie area. Capable of delivering 500 to 1000 liters per second, it suffered extensive damage from landslides triggered by the 2003 earthquake, compounded by drought conditions and operational challenges at the Rosamarina Dam over the previous two years. In 2017, faced with the threat of a severe water crisis, AMAP S.p.A. entrusted Danphix to rehabilitate the compromised sections using cutting-edge trenchless technologies for swift and effective repair.
The strategy employed included GPS mapping for precise localization of the underground pipeline and Geo-Radar technology to assess its condition. This thorough investigation identified critical damage to 1030 meters at Burgitabus and 640 meters at Scacciapidocchi. The repair approach leveraged tube coating technology for its flexibility and resilience against potential future landslides. This solution enabled the pipeline to maintain a flow capacity of 400-500 liters per second, restoring its vital distribution capability.
Primus Line® materials were selected for their exceptional flexibility and durability, reinforced with aramid fibers and a specialized plastic coating. Pipe diameters were adapted to meet specific operational and pressure requirements. Additionally, bespoke components were developed to ensure proper installation and seamless operation of the rehabilitated pipeline.
The project’s operational phases included site preparation, liner insertion, and the installation of steel fittings for connections. Rigorous quality control processes, including final testing and pipe disinfection, guaranteed the integrity of the work.
Outcome
This innovative project successfully restored the pipeline in a short timeframe, resolving a looming water crisis. It showcased the efficacy of advanced trenchless technologies in addressing critical infrastructure issues and set a benchmark for rehabilitating water pipelines across Italy.